City amends project contract

A design contract for the city’s planned wastewater treatment plant was amended Tuesday night, adding $228,918 to the city’s contract with Burns & McDonnell Engineering Company, Inc.

According to Mark Westenskow, the city’s public works director, the contract was originally planned to be amended in December after the city rejected bids for construction of the plant.

“We discovered that current world conditions, supply chain and the like are not kind to our project,” Westenskow said.

Westenskow said the city plans to redo the bids, but with a design package for the project that wo...

 

Reader Comments(0)

 
 
Rendered 04/15/2024 01:57